Steps an educational infrastructure construction & renovation client took to swiftly scale-up the operational efficiency.

Client Challenges

  • Undetermined Project costs.
  • Absence of alert mechanisms to check from exceeding the budget or deviating plans.
  • Double billing for same work/service or contractor billing for unperformed work/service.
  • Manipulating labour attendance and wage rate.
  • Postponement in project completion due to hiccups in stock delivery.
  • Project timeline extension due to fund crunch and unplanned activity.

PKC Solutions

  • Created analytical dashboard to gauge project-wise budget vs actuals.
  • System to ensure contractor payments are made against % of work completed.
  • Installed multilevel project-wise NMR attendance.
  • Placed a tracking system to eliminate overcharging of man-hour.
  • Management can compare supplier quotes and select the potential suppliers.
  • Circumvented stock imbalance issue by placing systems for stock requirement planning and centralize purchasing.

Results

  • 40% Reduction in average stock delivery time.
  • 85%-90% Timely closure of projects after implementing timeline tracking.
  • Quick and timely decisions aided in the accurate budget planning of new projects.
  • The status and deviation of Projects are now updated regularly.
  • Comprehensive cost analysis and study of each Project.
  • Centralized bulk purchase of stock reduced cost.
  • Record data of erstwhile projects aided in the accurate budget planning of new projects.

 